The master schedule provides information about client locations, cleanup frequencies, service days and assigned techs. On the list view it is possible to list clients per each tech, to reassign all clients at once from one tech to another or to export the schedule to CSV file.

Master schedule

To permanently change service days or tech for a client open a single location view > click on Edit resource > update the info > then Save

Change tech and service days

On the master schedule it is also possible to adjust client geolocation if it is not geocoded well on the map. To adjust geolocation go to single location view > click on three dots > Adjust Geolocation > drag location pin to desired position > Save.

Adjust client geolocation